Energy, RENEWABLE

200 MW Banca Stand-Alone BESS Project

YEAR

Project Development

READY to BUILD

LOCATION

Banca Romania

200 MW Banca Stand-Alone BESS Project

Project Overview

The Banca Stand-Alone Battery Energy Storage System (BESS) project, located in Banca, Romania, is a pivotal development in Romania’s renewable energy landscape. With a capacity of 200 MW and a storage duration of 2-4 hours, this project is designed to enhance grid stability, support renewable energy integration, and capitalize on multiple revenue streams.

Technical Specifications

  • Location: Banca, Vaslui County, Romania
  • BESS Capacity: 200 MW
  • Storage Duration: 2-4 hours (400-800 MWh)
  • Battery Type: Lithium-ion (LFP chemistry for safety and longevity)
  • Land Area: 10 hectares (secured through rental agreements)
  • Grid Connection: 220 kV high-voltage connection to Transelectrica’s network
  • Inverter Technology: Advanced string inverters with 98% efficiency
  • Cooling System: Liquid-cooled for optimal thermal management
  • EMS Software: Proprietary energy management system for real-time optimization

System Applications

  • Energy Arbitrage: Store low-cost energy during off-peak hours and sell during peak demand.
  • Frequency Regulation: Provide fast-response ancillary services to maintain grid frequency.
  • Grid Stability Services: Mitigate voltage fluctuations and support black-start capabilities.
  • Peak Shaving: Reduce demand charges by discharging during peak load periods.
  • Renewable Energy Integration: Smooth intermittent output from nearby wind and solar farms.
  • Capacity Market Participation: Secure revenue through Romania’s capacity market mechanisms.

Project Status

Current Stage: Pre-construction (Ready to Build)

  • Solution Study: Scheduled for completion in Q2 2025, covering technical design and grid integration.
  • Land Acquisition: 10 hectares secured via long-term rental agreements with local landowners.
  • Permitting: Environmental and construction permits in progress, leveraging Romania’s streamlined process (no EIA required per ANPM, July 2024).
  • EPC Selection: Tender process initiated, targeting local and international contractors with BESS expertise (e.g., Prime Batteries, ENEVO Group).
  • Grid Connection: Application submitted to Transelectrica for 220 kV connection, with 5% connection fee guarantee paid per Order 53/2024.

Next Milestones:

  • Q3 2025: Finalize EPC contracts and begin site preparation.

  • Q4 2025: Commence installation of battery modules and electrical infrastructure.
  • Mid-2026: Target grid connection and testing phase.

  • Q3 2026: Achieve commercial operation date (COD).