Energy, RENEWABLE

454 MWp Ialomita PV Project

YEAR

Project Development

Near to RTB

LOCATION

Ialomita Romania

454 MWp Ialomita PV Project

Project Overview

The Ialomita PV Project, located in Ialomita, Romania, is a large-scale photovoltaic (PV) initiative with a capacity of 454 MWp. This project aims to significantly contribute to Romania’s renewable energy goals by providing clean energy to the national grid.

Technical Specifications

  • Location: Ialomita, Romania
  • Capacity: 454 MWp
  • Type: Photovoltaic (PV)
  • Grid Connection: 400 kV high-voltage connection to Transelectrica’s network
  • Panel Type: High-efficiency monocrystalline solar panels
  • Land Area: Approximately 600 hectares (secured through rental agreements)
  • Inverter Technology: Advanced string inverters with 98.5% efficiency
  • Monitoring System: Real-time performance monitoring software

System Applications

  • Energy Generation: Produce clean energy to meet regional demand.
  • Grid Stability: Support Transelectrica’s grid with consistent renewable energy output.
  • Renewable Integration: Complement other renewable projects in the region.
  • Peak Shaving: Supply power during high-demand periods to reduce grid strain.
  • Capacity Market Participation: Potential revenue through Romania’s capacity market.

Project Status

Current Stage: Pre-construction (Ready to Build)

  • Solution Study: Scheduled for completion in Q2 2025, covering technical design and grid integration.
  • Land Acquisition: 600 hectares secured via long-term rental agreements.
  • Permitting: Environmental and construction permits in progress, leveraging Romania’s streamlined process.
  • Grid Connection: Application submitted to Transelectrica for 400 kV connection, with connection fee guarantee paid.
 

Next Milestones:

  • Q3 2025: Finalize EPC contracts and begin site preparation.
  • Q4 2025: Commence installation of solar panels and electrical infrastructure.
  • Mid-2026: Target grid connection and testing phase.
  • Q3 2026: Achieve commercial operation date (COD).

Strategic Importance

  • Grid Support: Enhances Romania’s National Energy System with substantial solar capacity.
  • Policy Alignment: Supports Romania’s 38.3% renewable energy target by 2030.
  • Local Impact: Creates jobs and stimulates economic growth in Ialomita.
  • Revenue Streams: Combines energy sales and capacity market participation for financial viability.